Basic Carrier Sizing


Step 1: List all cables and hoses.


Step 2: Determine B dimension (Inner Height) required by adding a safety factor (10% for cables, 20% for hoses) to the OD of the largest cable or hose.


Step 3: Determine A dimension (Inner Width) required by adding the ODs + appropriate safety factors (see Step 2) of all cables and hoses. If using vertical cavity separators (Page 13), add separator width. If using horizontal cavity dividers (Page 13), please consult with Gortrac at (800) 394-1547.


Step 4: Consult Sizing Index of the Quick Reference Guide (Pages 2-3) for appropriate series.


Step 5: Check C (Outer Width) and D (Outer Height) dimensions against potential space restrictions.


Cable/Hose Safety Factor:


Cables: + 10%     Hoses: + 20%


B = Cavity Height

Determined by the OD of the largest cable/hose + safety factor


A = Cavity Width

Determined by adding the ODs of all cables/hoses (= safety factor and divider widths)


C = Outer Width    D = Outer Height


Step 6: Select R (Minimum Bending Radius) by consulting cable/hose manufacturer's specifications


Step 7: Check K (Depot) and H (Curve Height) dimensions against potential space restrictions


R = Radius

K = Depot

H = Curve Height


Step 8: Determine required machine travel


Step 9: Consult the Gortrac Design Guide Specifications for CL (Curve Length) of the chosen carrier


Step 10: Carrier Length = Total Travel/2 + Distance offset from center + CL CL = (R x p) + (Pitch x 2)


 

Send Us Your Design